Dariya - Afif Road
Riyadh & Qassim, KSA
Project Description
The engineering services for the study and design of the Dualization of Dhariya/Al Kafiya/Al Hamada Afif Road, spanning 106 km, encompass a comprehensive scope to enhance connectivity and ensure safer transportation. The project includes the design and implementation of four interchanges to improve traffic flow and provide seamless access to adjacent areas. The design adheres to international and local highway standards, focusing on durability, safety, and sustainability.
Client
Scope of Work
- Field investigations including Traffic count
- Traffic Impact Study (TIS)
- Feasibility study for the various construction and operation alternatives for each of the proposed roads and interchanges according to the expected traffic volumes until the target year (20) years
- Assessment and Topographic Survey;
- Hydrological and Geotechnical Studies;
- Complete Highway geometric and pavement design;
- Structural analysis and complete design of crossing bridges;
- Quantities survey and Cost Estimate.
- Flood mitigation and protection works along the road
Project Highlights
Project Duration:
4 Months
Total Road Length:
106 km
4 interchanges for improved traffic flow and accessibility
Related Projects
Design Peer Review for the KAEC
Existing Air Traffic Control Tower - Gap Analysis
Hijra Road East Package 4&6
O-West Compound
Latin Quarter Project
Marsa Matrouh - Salloum Road Dualization Project
SODIC Villette
Marsa Alam Storm Drainage Networks
KEC - Design Review for ALYIAA OFFICES & AMENITIES
KEC - Design Review for AL-ALIYAA RESIDENCE